The Lelystad solar park has an installed capacity of 42 MWp, resulting from the two-phase construction: 28 MWp in the first phase and 14 MWp in the second phase.
No results found.
The Lelystad solar park has an installed capacity of 42 MWp, resulting from the two-phase construction: 28 MWp in the first phase and 14 MWp in the second phase.
After a construction period of around five months, Goldbeck Solar has completed its next project with the solar park in Lelystad, the Netherlands. As Lelystad is located below sea level, the loose soil posed a particular challenge for the company during construction. However, with the completion of the construction work, a new solar park has now been built there, which will enable citizens in and around Lelystad to benefit from sustainable energy generation in the future.